2011 Ontario Reliability Compliance Program Schedule
Each year NERC, NPCC Inc., and the IESO select a subset of reliability standards for monitoring. Market Participants are required to provide reliability compliance information under the IESOs Ontario Reliability Compliance Program (ORCP).
The schedule for reliability compliance submissions by market participants is shown in the table below. 2011 ORCP Schedule and History of Changes (Revised December 12, 2011 | Originally Published January 26, 2011).
Please note the forms below are for information purposes only. Market Participants must submit the electronic certification forms using the IESO Reliability Compliance Tool accessed via the IESO Web Portal.
| Included in 2010 IRCP? |
NERC Standards Group |
NERC Standard |
NPCC Document |
Description |
Reporting Frequency |
Target Submission Date |
Ontario Reporting Entity |
Form |
| Y |
PRC |
PRC-005-1
PRC-008-0
PRC-011-0
PRC-017-0
|
Directory 3 |
Maintenance Criteria for Bulk Power System Protection |
Annual |
Preliminary Submission 20-Jan-2011, Final Submission 31-May-2011 |
T, G, D, W |
1521 |
| Y |
PRC |
PRC-001-1 |
|
System Protection Coordination |
Annual |
13-Jul-11 |
T, G |
1637 |
| Y |
|
|
|
Emergency Preparedness Planning Market Rules Chapter 5 - Power System Reliability Market Manual 7.10 - Ontario Electricity Emergency Plan |
Annual |
13-Jul-11 |
T, G, D, W |
1608 |
| Y |
|
|
|
Emergency Restoration Planning Market Manual 7.8 - Ontario Power System Restoration Plan |
Annual |
13-Jul-11 |
T, G, D, W |
1609 |
| Y |
|
|
Directory 12 Section 5.4 |
Generator Underfrequency Protection Requirements |
Annual |
22-Aug-11 |
G |
1718 Survey |
| Y |
|
|
Directory 12 Section 5.2 |
Automatic Underfrequency Load Shedding consistent with NPCC's UFLS program requirement |
Annual |
22-Aug-11 |
T, D, W |
1719 Survey |
| Y |
|
|
Directory 12 Section 5.2 |
Automatic Underfrequency Load Shedding consistent with NPCC's UFLS program requirement |
Annual |
TBD |
T, D, W |
1518 Certification |
| Y |
FAC |
FAC-008-1 |
|
Facility Ratings Methodology |
Annual |
6-Sep-11 |
T, G, W |
1623 |
| Y |
FAC |
FAC-009-1 |
|
Establish and Communicate Facility Ratings |
Annual |
6-Sep-11 |
T, G, W |
1624 |
| New |
PRC |
PRC-023-1 |
|
Transmission Relay Loadability |
Annual |
31-May-12 |
T, G, D |
1738 |
| Y |
CIP |
CIP-001-1a |
|
Sabotage Reporting |
Annual |
5-Oct-11 |
T, G, D, W |
1610 |
| Y |
CIP |
CIP-002-3 |
|
Cyber Security Critical Cyber Asset Identification (a) |
Annual |
5-Oct-11 |
T, G, W |
1694 |
| Y |
CIP |
CIP-003-3 |
|
Cyber Security Security Management Controls (a) |
Annual |
5-Oct-11 |
T, G, W |
1695 |
| Y |
CIP |
CIP-004-3 |
|
Cyber Security Personnel & Training (a) |
Annual |
5-Oct-11 |
T, G, W |
1696 |
| Y |
CIP |
CIP-005-3 |
|
Cyber Security Electronic Security Perimeter(s) (a) |
Annual |
5-Oct-11 |
T, G, W |
1697 |
| Y |
CIP |
CIP-006-3c |
|
Cyber Security Physical Security of Critical Cyber Assets (a) |
Annual |
5-Oct-11 |
T, G, W |
1698 |
| Y |
CIP |
CIP-007-3 |
|
Cyber Security Systems Security Management (a) |
Annual |
5-Oct-11 |
T, G, W |
1699 |
| Y |
CIP |
CIP-008-3 |
|
Cyber Security Incident Reporting and Response Planning (a) |
Annual |
5-Oct-11 |
T, G, W |
1700 |
| Y |
CIP |
CIP-009-3 |
|
Cyber Security Recovery Plans for Critical Cyber Assets (a) |
Annual |
5-Oct-11 |
T, G, W |
1701 |
| Y |
|
|
Directory 8 Section 5.7 |
Key Facility Critical Component Testing (c) |
Annual |
7-Nov-11 |
T, G |
1520 |
| Y |
FAC |
FAC-003-1 |
|
Transmission Vegetation Management Program |
Annual |
TBD |
T |
1526 |
| Y |
NUC |
NUC-001-2 |
|
Nuclear Plant Interface Coordination (b) |
Annual |
31-May-12 |
T, G, D |
1704 |
| Y |
PRC |
PRC-004-1
PRC-004-1a
|
|
Analysis and Mitigation of Transmission and Generation Protection System Misoperations |
Annual |
31-May-12 |
T, G, D, W |
1522 & 1523 |
| Y |
TOP |
TOP-002-2a TOP-002-2b |
|
Normal Operations Planning |
Annual |
31-May-12 |
G |
1643 |
| Y |
VAR |
VAR-002-1.1b |
|
Generator Operation for Maintaining Network Voltage Schedules |
Annual |
31-May-12 |
G |
1571 |
| Y |
EOP |
EOP-009-0 |
|
Documentation of Blackstart Generating Unit Test Results (d) |
Annual |
31-May-12 |
G |
1532 |
| Y |
|
|
Directory 9
Directory 10
|
Generator Gross/Net Real Power Capability & Generator Gross/Net Reactive Power Capability |
Upon request by IESO |
|
G |
1635 & 1710 |
| New |
PRC |
PRC-016-0.1 |
|
Special Protection System Misoperations |
Exception Reporting |
|
T, G, D |
|
| Y |
FAC |
FAC-003-1 |
|
Transmission Vegetation Management Program |
Exception Reporting |
|
T |
1527 |
T - Transmitter; G - Generator; D - Distributor; W - Connected Wholesale Customer
(a) Applicable to those market participants identified by the IESO as owners of Critical Assets.
(b) Applicable only to those market participants notified by the IESO.
(c) Applicable to those market participants identified by the IESO as owners of key facilities.
(d) Applicable to certified black start facility owners.
|