Ontario’s Long Term Energy Plan reinforces the investment focus on renewable generation under the Green Energy and Green Economy Act (GEA) and the Ontario Power Authority’s Feed-In-Tariff (FIT) program. The Plan acknowledges the significant commitments made to date - 5,800 MW of variable generation projects, primarily wind, are underway and are expected to be in commercial operation by the end of 2012, with 10,700 MW targeted for 2018.
The IESO needs to be in a position to register and incorporate this variable generation into power system operations and IESO-administered markets. This stakeholder initiative will discuss design principles for forecasting, dispatch, visibility and future markets for wind and solar generation, as appropriate. This initiative builds on the forecasting work previously done in Renewable and Embedded Generation (SE-57).
Renewable Integration is of interest to many stakeholders. Local distribution companies, generators of all types (particularly wind and solar generators), and energy agencies, will have the most interest in this initiative, and its related policies, standards, and market rule changes.
| Date |
Activity |
Expected Actions |
May 22, 2013
Agenda |
SE-91 Meeting
• Communication
• Centralized Forecasting Accuracy
• Centralized Forecasting Report Changes
• Market Manual Changes
|
|
February 21, 2013
Agenda
Minutes |
SE-91 Meeting
• Communication
• Market Schedule and CMSC Proposal
• Draft MR-00402-R00: Market Schedule and CMSC for Variable Generation – True-Up
• Centralized Forecasts in SSRs and SAAs
• Communication Pathways for Variable Generator Dispatch
• Market Participant Outreach and Readiness
Stakeholder Feedback
• Ontario Power Generation
|
|
December 13, 2012
Agenda
Minutes |
SE-91 Meeting
• Communication
• Dispatch Technical Working Group Summary
• Floor Price Focus Group Summary
• Variable Generation Dispatch Detailed Design Document
Stakeholder Feedback
• Brookfield Renewable Energy Group
• Enbridge Inc.
|
|
November 9, 2012 Minutes |
Fourth meeting of the Floor Price Focus Group
• Communication
(Revised)
• Floor Price Update Document
• Floor Price Presentation |
|
| August 22, 2012 |
Stakeholder Feedback
• Ontario Power Generation
• Ontario Waterpower Association
|
|
| August 16, 2012
|
• Communication - Dispatching Variable Generation Market Rule Amendments Posted |
|
August 8, 2012
Agenda
Minutes
|
• Communication
• Floor Price Update Presentation - Revised
• Market Schedule and Congestion Management Settlement Credit, and SBG Control Actions
• Surplus Baseload Generation Explanation Document
• Stakeholder Response Spreadsheet |
|
| July 12, 2012 |
• Communication - Market rule amendments for dispatch and floor prices posted |
|
| July 11, 2012 |
Stakeholder Feedback
• Enbridge
• Kruger Energy
• Ontario Power Generation
• Power Advisory LLC - for IPR-GDF, NextEra, Pattern and Samsung
• Rob Cary & Associates
|
|
June 27, 2012
Agenda
Minutes |
Third meeting of the Floor Price Focus Group
• Communication
• Presentation on Floor Prices - Revised
• Centralized Forecasting Publication Requirements - Revised |
|
May 3, 2012
Agenda
Minutes |
SE-91 Meeting
• Communication
• Update on Floor Price Focus Group (Updated May 4, 2012)
• IESO Response to Stakeholder Comments – Floor Price Focus Group
• Centralized Forecasting: Update and Publishing Requirements
Stakeholder Feedback
• Hydro One (Received June 29, 2012)
• Enbridge
• Ontario Power Generation
• Power Workers Union - Proposed Variable Generation Forecast System
• Power Workers Union - Floor Price |
The IESO will provide an update on the Floor Price Focus Group, including additional feedback and supporting analysis, and discuss centralized forecasting publication requirements. |
| March 26, 2012 |
• Communication, Floor Price Focus Group Update |
|
January 24, 2012
Agenda
Minutes |
Second meeting of the Floor Price Focus Group
• Communication
• Presentation (Revised January 25, 2012)
• Stakeholder Submission and Response Spreadsheet
• IESO Comments on a Dispatch Down Service |
The Floor Price Focus Group will review and discuss Market Participant submissions on the IESO’s Dispatch Order for Baseload Generation discussion paper. The IESO will present responses to Market Participant feedback, provide supporting analysis, and discuss next steps. |
December 19, 2011 |
Deadline to submit feedback on the Dispatch Order for Baseload Generation Discussion Paper
• Communication Stakeholder Feedback • Brookfield Power • Enbridge • Ontario Power Generation • Ontario Waterpower Association • Power Workers Union • Power Advisory LLC – for IPR-GDF Suez North America; NextEra Energy Canada ULC; Pattern Energy Group LP; and Samsung Renewable Energy Inc.
• RES Group |
The IESO is seeking to clarify the technical and regulatory limitations of baseload generators, as outlined in the discussion paper.
Please submit your response to stakeholder.engagement@ieso.ca
|
November 21, 2011
Agenda
Minutes |
First meeting of the Floor Price Focus Group
• Communication
• Dispatch Order for Baseload Generation Discussion Paper
• Presentation |
|
November 7, 2011 |
First meeting of the Dispatch Technical Working Group – updates will be available on the DTWG webpage
• Communication |
|
October 21, 2011
Agenda |
Webinar for embedded generators
(additional information to be posted)
• Communication
• Presentation |
|
September 26, 2011
Agenda |
LDC Webinar – “Renewable Integration - What it means to LDCs and their Customers”
Communication: Request for Information from LDCs on Renewable Generation Projects
• Presentation
Stakeholder Feedback
• Summary of Session Feedback |
|
| September 19, 2011 |
Proposed changes to IESO Documents posted on Pending Changes
• Multiprotocol Label Switching and Alternative Communications for Medium Performance Facilities, IMDC-0169
• changes to the Participant Technical Reference Manual to enable VPN and LDC communication
• Variable Generation Requirements, IMDC-0170
• changes to Market Manual 1.2 detailing facility data and operational monitoring requirements (static and dynamic data) for wind and solar generators. |
Stakeholders to comment on proposed changes by September 30 to pending.changes@ieso.ca. |
| July 28, 2011 |
Variable generation data registration forms posted for comment on Pending Changes
• Application to Register Variable Generation Facility Data - Form 1735
• Wind Generation Facility Data - Form 1736
• Solar Generation Facility Data - Form 1737
Market Rule Reference
• MR-00362-R01, Renewable Integration - Forecasting, Centralized Forecasting - Data Obligations |
Once finalized, variable generators will use these forms to submit site specific data for centralized forecasting and visibility purposes. |
| May 12, 2011 |
New Dispatch Technical Working Group – updates are available on the Dispatch Technical Working Group webpage |
|
May 12, 2011
Agenda
Minutes |
Meeting with stakeholders to provide an update on work completed through the Visibility Technical Working Group; discuss design details associated with Design Principles 7, 8 and 9; and provide an overview of the next steps.
• Communication
• Presentation
• Visibility Technical Working Group Summary
• Dispatch Variable Generation Resources discussion paper
Stakeholder Feedback
• Summary of Session Feedback |
All meeting materials will be posted no less than 10 business days prior to the meeting. |
March 9, 2011
|
Final Design Principles Posted
• SE-91 Renewable Integration Final Design Principles
• Communication |
|
March 3, 2011
|
First meeting of Visibility Technical Working Group – updates are available on the Visibility Technical Working Group webpage |
|
March 2, 2011 |
Presentation at the Stakeholder Advisory Committee by Paul Murphy, President and CEO on Renewable Integration
• Presentation |
|
March 2, 2011
Agenda
Minutes |
The IESO will respond to stakeholder feedback, provide some additional background information in support of the Design Principles, and discuss next steps.
• Meeting Notice
• Presentation
• IESO Responses to Stakeholder Feedback
• Appendix 1 – Stakeholder Feedback
• Appendix 2 – ISO Comparison Table
• Additional Stakeholder Feedback from RES Group |
All meeting materials will be posted no less than five business days prior to the meeting
Presentation/Discussion |
| February 22, 2011 |
Conference call to discuss the Terms of Reference for the Visibility Technical Working Group and updated Stakeholder Engagement Plan
• Visibility Technical Working Group – Draft Terms of Reference
• Stakeholder Engagement Plan – Updated February 15, 2011
• Communication |
Deadline for stakeholder feedback on the Terms of Reference and the updated Stakeholder Engagement Plan is February 24, 2011
Deadline for stakeholders to apply for membership on Visibility Technical Working Group is February 24, 2011 |
February 1, 2011
Agenda
Minutes (Revised) |
Conference call to provide a summary of feedback on comments received, and ask clarifying questions.
IESO will provide an update on next steps and future meetings.
• Communication update
• Design Principles Feedback – Presentation
• Design Principles Feedback – Results |
IESO to post stakeholder feedback Presentation/Discussion |
January 17, 2011 |
Stakeholder Feedback
• AWS True Power – Rec’d Feb 7
• Tom Adams - Rec'd Feb. 2
• Brookfield Renewable Power - Rec'd Jan. 26
• Bruce Power - Rec'd Jan. 26
• CanWEA - Rec'd Jan. 21
• Enbridge - Rec'd Feb. 4
• Hydro One - Rec'd Jan. 21
• Invenergy LLC - Rec'd Jan. 28
• Northland Power - Rec'd Jan. 17
• OPG - Rec'd Jan. 17
• Parker Gallant - Rec’d Feb 3
• Penn Energy Renewables - Rec'd Jan. 16
• Power Advisory LLC - for International Power, NextEra, Pattern and Samsung - Rec'd Jan. 17
• Power Workers Union - Rec'd Jan. 17
• RES Group - Rec'd Jan. 17
• SunEdison - Rec'd Jan. 17
• TransAlta - Rec'd Jan. 17
• TransCanada Energy - Rec’d Feb 9 |
IESO to post stakeholder feedback |
January 11, 2011
Agenda
Minutes |
Meeting with stakeholders to present Design Principles (2nd meeting for those who cannot attend Dec. 16)*
Stakeholder Feedback
• Summary of Session Feedback |
Deadline for stakeholder feedback by January 17, 2011
*See December 16, 2010 Presentation |
December 16, 2010
Agenda
Minutes |
Meeting with stakeholders to present Design Principles
• Presentation
Stakeholder Feedback
• Summary of Session Feedback |
Deadline for stakeholder feedback by January 17, 2011 |
| December 9, 2010 |
Renewable Integration Design Principles for feedback along with OPA letters.
• IESO Cover Letter
• Design Principles on Renewable Integration
• OPA Letter to RESOP, RESI, RESII
• OPA Letter to FIT, RESIII, HCI
Final Stakeholder Plan posted.
• Final Stakeholder Plan
• Communication |
Deadline for stakeholder feedback by January 17, 2011 |
| November 18, 2010 |
Stakeholder Feedback
• APPrO
• John MacKenzie
• NextEra
• Power Workers Union
• Richard Penn
• SunEdison
• IESO Reponse to Stakeholder Feedback |
Stakeholders to provide written feedback by November 18, 2010 |
| November 11, 2010 |
Communication – Reminder for Feedback on Draft Stakeholder Plan |
|
| November 4, 2010 |
Post and communicate stakeholder engagement plan for comments
• Communication
• Draft Stakeholder Engagement Plan |
|