The IESO is establishing a Market Trials Working Group (MTWG) under Stakeholder Engagement Plan #73 (SE-73) in order to assist the IESO in the planning and execution of the EDAC Market Trials. This working group is primarily for those organizations who will be involved in the operational component of the trials for EDAC.
Market Trials for EDAC are currently scheduled to begin in May 2011, with an expected fall 2011 in-service date.
The IESO has established the Project Advisory Group under Stakeholder Engagement Plan #73 (SE-73) in order to facilitate project updates to stakeholders during the IT Design and Build phase of the EDAC project and carry out internal acceptance testing. This group will be consulted on important market facing milestones that will occur in 2011 such as training, development of market manuals, ability testing and scheduling for both Market Trials and in-service.
Market Trials for EDAC are currently scheduled to begin in mid-2011, with an expected fall 2011 in-service date.
Date Agenda/Minutes |
Group |
Supporting Material |
Expected Actions |
October 7, 2011
EDAC External Review |
PAG MTWG |
EDAC Settlements external review report |
Reference |
| October 7, 2011 |
MTWG |
EDAC Market Trials Testing Report, v1.0 |
Reference |
October 4, 2011
Agenda
Minutes |
MTWG |
Impact of Locational Marginal Prices (LMP) calculation in Day Ahead and real Time
Miscellaneous
EDAC Market Trials Testing Report |
Information |
September 30, 2011
Agenda |
|
Workshop Invitation - Preparing for Enhanced Day-Ahead Commitment Process (DACP) Participation
Presentation |
|
September 9, 2011
Agenda
Minutes |
MTWG |
Action Item Summary updates from July 17, 2011
Market Trials Defect Report
EDAC In-Service Timeline
RT-GCG Settlement Treatment
EDAC Final Release Plan
MPI Portalization Project Presentation
RT-GCG Settlement Treatment Presentation
|
Information |
| September 8, 2011 |
|
Form 1181, 1552, 1721, 1702 |
Reference |
| August 26, 2011 EDAC Settlements Market Trials |
MTWG |
EDAC Settlements Market Trials Test Scenarios v3.0
(revised Appendix A: Compressed Settlements Calendar and Schedule) |
Reference |
August 18, 2011
EDAC External Review |
PAG MTWG |
Day-Ahead Calculation Engine (DACE) external review report |
Reference |
August 11, 2011
EDAC Forms |
|
Form 1181, 1552, 1721, 1702 |
Reference |
August 5, 2011
EDAC Settlements Market Trials |
MTWG |
EDAC Settlements Market Trials Test Scenarios v2.0 |
Reference |
July 26, 2011
EDAC Settlements Market Trials |
MTWG |
EDAC Market Trials Test Plan v2.0
Market Manuals baselined for EDAC Settlements Market Trials (v4.0)
MM5 Settlements Part 5.5 Physical Markets Settlement Statements v4.0
MM9 Part 9.5 Settlement for the Day-Ahead Commitment Process v4.0
IESO Charge Types and Equations v4.0
EDAC Settlements Market Trials Test Scenarios v1.0 |
Reference |
July 7, 2011
Agenda
Minutes |
MTWG |
EDAC Market Trials Test Plan v1.1 |
Review and Comment |
June 30, 2011
Agenda
Minutes |
MTWG |
Settlements Market Trials Overview
Settlements Market Trials Scenarios
Settlements Market Trials Approach |
Review and Comment |
May 24, 2011 EDAC Market Trials Ability Testing |
MTWG |
• Ability Testing for Market Trials Guideline and Checklist |
Reference |
May 24, 2011
EDAC Market Trials Manuals and Forms |
MTWG |
Market Manuals (Operations) EDAC Baseline 4.0 for Market Trials:
• Market Manual 1: Part 1.1
• Market Manual 1: Part 1.2
• Market Manual 4: Part 4.0
• Market Manual 4: Part 4.2
• Market Manual 4: Part 4.3
• Market Manual 7: Part 7.2
• Market Manual 7: Part 7.3
• Market Manual 9: Part 9.0
• Market Manual 9: Part 9.1
• Market Manual 9: Part 9.2
• Market Manual 9: Part 9.3
• Market Manual 9: Part 9.4
EDAC Enrolment Forms (Word Documents) EDAC Baseline 4.0 for Market Trials:
• IMO_FORM_1181 Facility Profile
• IMO_FORM_1152 Real Time Generation Cost Guarantee and Day-Ahead production Cost Guarantee Data Form
• IESO_FORM_1702 Combined Cycle Plant Form
• IESO_FORM_1721 Implementation of Three-Part Offers |
Reference |
May 19, 2011
Agenda
Minutes |
MTWG |
• Market Trials Timelines and Key Events v1.0
• Market Trials Portal Structure
• Market Trials Test Case Sample
• Market Trials Test Execution Form - Sample |
Information |
| May 12, 2011 |
MTWG |
• Communication |
|
May 2, 2011
Agenda
Minutes |
MTWG |
• EDAC Market Trials Administration |
Information |
May 2, 2011
Agenda
Minutes |
PAG |
• Market Manual 9.5 Settlement for the Day-Ahead Commitment Process , v3.0
• IESO Charge Types and Equations v0.1
• Link to IESO Settlements Test Cases |
Information |
| March 31, 2011 |
|
• Communication
• Draft Stakeholder Engagement Plan (SE-73) Market Trials Working Group (Revised)
• Draft Terms of Reference Market Trials Working Group (Revised)
|
Review and provide comments |
March 24, 2011
Agenda
Minutes |
|
• Draft Stakeholder Engagement Plan (SE-73) Market Trials Working Group
• Draft Terms of Reference Market Trials Working Group
• Market Trials Test Plan 3rd draft |
Review and provide comments |
February 24, 2011
Agenda
Minutes |
|
Action Item #45
Market Trials test Plan 2nd draft
Summary of Market Manual Revisions
DACP Market Place training Guide
|
For discussions
Review and provide comments
Information |
January 24, 2011
Agenda
Minutes
|
|
EDAC project – IESO Internal Testing Summary |
|
| December 17, 2010 |
|
Market Manuals EDAC Baseline 2.0
• Market Manual 1: Part 1.1
• Market Manual 1: Part 1.2
• Market Manual 4: Part 4.0
• Market Manual 4: Part 4.2
• Market Manual 4: Part 4.3
• Market Manual 5: Part 5.5
• Market Manual 7: Part 7.2
• Market Manual 7: Part 7.3
• Market Manual 9: Part 9.0
• Market Manual 9: Part 9.1
• Market Manual 9: Part 9.2
• Market Manual 9: Part 9.3
• Market Manual 9: Part 9.4
• Market Manual 9: Part 9.5 |
Reference |
| December 8, 2010 |
|
EDAC Enrolment Forms version 1.0 for EDAC Test Data:
|
Submit completed forms to IESO EDAC project at edac@ieso.ca
or by fax to 905-403-6902 by December 17, 2010. |
November 30, 2010
Agenda
Minutes |
|
• Enrol Facility Process
• Walk Through Presentation
• Draft DACP Marketplace Training Guide v0.2
• EDAC Enrolment Forms (Word documents)
• Market Manual Updates from September 30th PAG
• Summary of Updates
• Revised Market Manuals (red-line documents)
• Market Trials Test Plan |
Review and provide comments |
October 28, 2010
Cancelled |
|
• Market Manuals (revised to incorporate comments; red-line documents)
• Structure of Market Trials v2.0 (revised to incorporate comments, red-line document)
• Market Rule Amendment True-Ups (revised to incorporate comments) |
Review and provide comments |
September 30, 2010
Agenda
Minutes |
|
• Revised Market Manual 9.5 v0.4- Settlement for the Day Ahead Commitment Process
• Revised Market Manual 9.5 - Settlement for the Day Ahead Commitment Process
• Summary of Market Manual Revisions
• Market Manual 1: Part 1.1
IESO_Form_1721
• Market Manual 1: Part 1.2
• Market Manual 2: Part 2.14
• Market Manual 4: Part 4.0
• Market Manual 4: Part 4.2
• Market Manual 4: Part 4.3
• Market Manual 5: Part 5.5
• Market Manual 7: Part 7.2
• Market Manual 7: Part 7.3
• DACP Failure Report Set
• Procedure for Failure to Load Commitments
• Submit 3 Part Offers
• Market Rules True-up for EDAC
• Structure of Market Trials
|
• Review draft Market Manuals for Enhanced DACP
• Update on EDAC project implementation
• Market Rules updates required
• Review of Market Trials structure |
August 26, 2010
Agenda
Minutes |
|
• Settlement under Admin Pricing
• Introduction to EDAC Market Rule True-Ups
• Comments on EDAC Market Manuals:
• OPG
• Sithe
• Market Manual 9.5 Settlement for the Day Ahead Commitment Process
• Response to comments on MM9 Parts 9.0 to 9.4 |
• Review Draft Market Manuals for Enhanced DACP
• Update on EDAC Project Implementation
• Market Rules Updates Required
• Market Participant Requirements for Market Trials |
July 15, 2010
Agenda
Minutes (Final) |
|
• Revised Terms of Reference
• Market Manual 9.0
• Market Manual 9.1
• Market Manual 9.2
• Market Manual 9.3
• Market Manual 9.4
• Market Trials Planning |
|
June 11, 2010
Agenda
Minutes (Final) |
|
• Draft Terms of Reference
• Schedule of Stakeholder Activities
• Changes to Market Manuals
• EDAC Timeline |
• Review Draft Terms of Reference |
Note: From June through August 2011, weekly conference calls will be held for market trials operation.
Materials, including agendas for the working group will be available to members within the web portal and on this webpage. For any assistance, send a request to stakeholder.engagement@ieso.ca.