Inter-market Trading of Operating Reserve (SE-60)
Current market rules allow the IESO to obtain non-spinning operating reserve from commercial imports. The IESO-administered markets, as they are now, do not permit the commercial exporting of operating reserve from Ontario to neighbouring jurisdictions. For reciprocity reasons, importing of OR will also be examined.
Electricity reliability and the market impacts of these initiatives are of interest to all stakeholders. Dispatchable consumers and generators provide OR and consumers pay the cost of procuring OR. The exporting and importing of OR will also have an interest to traders who conduct transactions between neighbouring electricity markets.
The goal of this stakeholder plan is to provide stakeholders the opportunity to provide feedback to IESO staff on the impact of this change on their business and on the market in order for IESO staff to make a complete recommendation to the IESO Board.
Stakeholder Plan (Draft)
Stakeholder Plan (Revised, August 18, 2008)
Proposed Activities
Date Agenda/Minutes |
Supporting Material |
Expected Actions |
| October 29, 2008 |
As proposed at the August 19, 2008 Market Pricing Working Group meeting, the IESO will not be proceeding with further
work on this initiative See page 3 of Minutes |
Management decision announced at Market Pricing Working Group meeting |
| September 12, 2008 |
Due date for written comments on final recommendations
• No feedback received |
Deliberation — Input requested from sector members |
| August 19, 2008 |
Present recommendations to the Market Pricing Working Group
• Final Recommendation
• Presentation |
Deliberation — Recommendations presented |
| Mid August, 2008 |
Publish recommendations incorporating stakeholder input
• See Market Pricing Working Group, August 19 meeting, item 3, issue 39 |
Deliberation — IESO to post revised recommendations |
| June 30, 2008 |
Deadline for written comments on recommendations
• No comments received outside those already posted under May 30 |
Deliberation — IESO to post written feedback from stakeholders |
| June 5, 2008 |
Develop and publish recommendations for discussion and stakeholder input
• Item 3 at Market Pricing Working Group meeting |
Deliberation — Stakeholder written feedback |
| May 30, 2008 |
Deadline for feedback on analysis and findings from May 16, 2008 MPWG presentation
Stakeholder Feedback
• Ontario Power Generation |
|
| March to May, 2008 |
Engage the Market Pricing Working Group in dialogue around the issues, impacts and outcomes |
Dialogue — Stakeholder input/discussion |
| April 21, 2008 |
Post revised stakeholder engagement plan along with IESO response to stakeholder feedback
• No comments received |
IESO to post revised stakeholder engagement plan |
| April 17, 2008 |
Deadline for feedback from stakeholders on the stakeholder engagement plan |
IESO to post feedback from stakeholders |
| April 3, 2008 |
Post and communicate the stakeholder engagement plan for feedback from stakeholders |
Stakeholder written feedback |
|
| |