Status of Committed Generation Project Queue
The following are the possible states of the status column:
- "Complete" indicates that reports are available for viewing.
- "Active" indicates that the assessment is in progress.
Last Updated:
September 2, 2008
| Queue Position |
CAA ID & Date used for Queue Position |
Proponent |
Location |
Project Type |
Proposed Size |
In-service Date |
Current Status of: |
Report |
| Preliminary Assessment |
System Impact Assessment |
| 2 |
2000-003 Jan 16, 1999 |
NORTHLAND POWER INC. |
Thorold |
New Generation |
294 MW
|
Q2-2009
|
Complete |
Complete |
Preliminary Assessment Draft Report Attachment 1 Addendum
|
| 6 |
2000-008 Nov 15, 1999 |
SITHE CANADIAN HOLDINGS INC. |
Goreway, Brampton |
New Generation |
749.1 MVA 447 MVA
|
Under Construction Q2-2008
|
N/A |
Complete |
Report Addendum
|
| 25 |
2001-040 Jul 19, 2001 |
ONTARIO POWER GENERATION INC. |
Hearn Site (Portlands Energy Centre) |
New Generation |
250 MW 300 MW
|
Q2-2008 Q4-2009
|
Complete |
N/A |
Preliminary Assessment Addendum Addendum 2
|
| 54 |
2002-077 Nov 29, 2002 |
BROOKFIELD WIND POWER CORPORATION |
Collingwood |
New Generation |
49.5 MW
|
N/A
|
Complete |
N/A |
Preliminary Assessment
|
| 57 |
2002-068 Dec 4, 2002 |
ONTARIO POWER GENERATION INC. |
Beck GS #2 |
New Generation |
192 MW
|
Q3-2004
|
Complete |
N/A |
Preliminary Assessment
|
| 62 |
2002-081 Dec 10, 2002 |
EPCOR POWER DEVELOPMENT CORPORATION |
Goderich |
New Generation |
39.6 MW
|
In-Service
|
Complete |
Complete |
Preliminary Assessment
|
| 81 |
2003-106 Sep 22, 2003 |
AIM POWERGEN CORPORATION |
Port Burwell (Lake Erie Northshore) |
New Generation |
99 MW
|
In-Service
|
- |
Complete |
Report Appendix
|
| 83 |
2003-107 Nov 26, 2003 |
ENERSOURCE HYDRO MISSISSAUGA INC. |
Pearson IA |
New Generation |
117 MW
|
In-Service
|
- |
Complete |
Report Addendum
|
| 87 |
2003-103 Feb 4, 2004 |
CANADIAN HYDRO DEVELOPERS INC |
Melancthon Township |
New Generation |
68 MW 132 MW
|
In-Service Q4-2008
|
- |
Complete |
Report Appendix Addendum
|
| 89 |
2004-114 Mar 17, 2004 |
EPCOR POWER DEVELOPMENT CORPORATION |
Ashfield-Colborne |
New Generation |
158.7 MW
|
N/A
|
- |
Complete |
Report
|
| 90 |
2004-111 Mar 22, 2004 |
CANADIAN HYDRO DEVELOPERS INC |
Wolfe Island |
New Generation |
197.8 MW
|
Q4-2008
|
- |
Complete |
Report
|
| 92 |
2004-117 Apr 21, 2004 |
BROOKFIELD WIND POWER CORPORATION |
Sault St. Marie (Prince Park) |
New Generation |
99 MW 101 MW
|
In-Service In-Service
|
- |
Complete |
Report Appendix
|
| 96 |
2004-121 May 20, 2004 |
ENBRIDGE ONTARIO WIND POWER LP |
Kincardine |
New Generation |
100 MW
|
Under Construction
|
- |
Complete |
Report Report
|
| 99 |
2004-125 May 25, 2004 |
SUNCOR ENERGY INC. |
Shores of Lake Huron (Ripley) |
New Generation |
75 MW
|
In-Service
|
- |
Complete |
Report
|
| 100 |
2004-128 May 25, 2004 |
BEGETEKONG POWER CORPORATION |
Northeast of Marathon, White River (Umbata Falls) |
New Generation |
20.5 MW
|
Q1-2007
|
- |
Complete |
Report
|
| 116 |
2004-155 Aug 12, 2004 |
CANADIAN HYDRO DEVELOPERS INC |
Bradburn, ON (Island Falls) |
New Generation |
20 MW
|
Under Construction
|
- |
Complete |
Report
|
| 123 |
2004-167 Nov 4, 2004 |
GREENFIELD ENERGY CENTRE, LP |
Courtright, Lambton County |
New Generation |
1195 MW
|
Under Construction
|
- |
Complete |
Report Addendum Addendum#2
|
| 130 |
2004-175 Nov 24, 2004 |
ALGOMA STEEL INC. |
Sault Ste. Marie Plant |
New Generation |
103 MW
|
Under Construction
|
- |
Active |
|
| 134 |
2004-178 Nov 30, 2004 |
GREENFIELD SOUTH POWER |
Mississauga, ON |
New Generation |
284 MW
|
Q4-2009
|
- |
Complete |
Final Report
|
| 142 |
2004-187 Dec 9, 2004 |
ST. CLAIR POWER LP |
Lake St. Clair Area, Ontario |
New Generation |
688 MW
|
Under Construction
|
- |
Complete |
Report Addendum Addendum#2
|
| 146 |
2004-163 Jan 17, 2005 |
BRUCE POWER INC. |
Bruce A GS |
New Generation |
1870 MW
|
Q2-2009
|
- |
Active |
|
| 148 |
2004-143 Feb 5, 2005 |
ENBRIDGE ONTARIO WIND POWER LP |
Near Kincardine |
New Generation |
100 MW
|
Under Construction
|
- |
Complete |
Report
|
| 159 |
2005-203 Aug 5, 2005 |
KRUGER INC. |
Port Alma |
New Generation |
101 MW
|
Q4-2008
|
- |
Complete |
Report
|
| 161 |
2006-234 Aug 3, 2006 |
PRISTINE POWER INC. |
1000 Henry Ford Centre Drive, Windsor, ON M9A 7E8 |
New Generation |
99 MW
|
Q2-2009
|
- |
Complete |
Report Addendum 1
|
| 163 |
2007-255 Jun 5, 2007 |
SOAVE HYDROPONICS COMPANY |
1400 Rd. 3 East, Kingsville, Ontario |
New Generation |
12 MW
|
Q4-2007
|
- |
Active |
Final Draft Report
|
| 166 |
2007-261 Feb 21, 2008 |
FORT CHICAGO DISTRICT ENERGY LTD. |
London, Ontario |
New Generation |
22 MVA
|
Q2-2008
|
- |
Complete |
Final Report
|
| 167 |
2006-232 Jan 15, 2007 |
TRANSCANADA ENERGY LTD. |
Town of Halton Hills (401 Industrial Corridor) |
New Generation |
600 MW
|
Under Construction
|
- |
Complete |
Final Report
|
|
| |