This list contains all transmission, load, generation and ancillary services connection proposals that have submitted an SIA application on or after April 30, 2005 and subsequently executed an SIA agreement. Queuing principles are not applicable to these proposals. Links are provided for SIA reports.
| CAA ID |
Proponent |
Location |
Project Type |
Proposed Size |
In-service Date |
Current Status of System Impact Assessment |
Report |
| 2004-176 |
CANADIAN NIAGARA POWER |
Cornwall, Eastern Ontario |
Transmission |
150 MVAR
|
N/A
|
Complete |
Final Report Addendum 1
|
| 2005-201 |
VECTOR WIND ENERGY INC. |
Amherst Island |
New Generation |
24 MW
|
Q4-2007
|
On-Hold |
|
| 2005-202 |
POWERSTREAM INC. |
8000 Dufferin St., Vaughan, ON |
New Supply Point |
175 MW
|
In-Service
|
Complete |
Report
|
| 2005-204 |
VISION QUEST WINDELECTRIC |
Amberley, Bruce County & Ashfield, Huron Ontario |
New Generation |
75 MW
|
|
On-Hold |
|
| 2005-205 |
GREEN BREEZE |
Central Huron Municipality, Huron County |
New Generation |
79.5 MW
|
Q3-2007
|
On-Hold |
|
| 2005-206 |
BARRINGTON WIND ENERGY LTD. |
Concession A, 9 and 10; Huron-Kinloss Township |
New Generation |
18 MW
|
-
|
Withdrawn |
|
| 2005-207 |
FIVE NATIONS ENERGY INC |
Fort Albany TS |
New Supply Point |
20 MVA
|
Under Construction
|
Complete |
Report
|
| 2005-208 |
HYDRO ONE NETWORKS INC. |
Kenora |
Interconnection |
400 MW
|
N/A
|
On-Hold |
|
| 2006-209 |
HYDRO ONE NETWORKS INC. |
Oshawa Area |
New Supply Point |
250 MVA
|
Q2-2010
|
Active |
Final Draft Report
|
| 2006-211 |
HYDRO ONE NETWORKS INC. |
King Township or East Gwillimbury |
New Supply Point |
50.4 MVAR 175 MVAR
|
Q1-2009 Q2-2009
|
Active |
Phase I Report Phase II Final Draft Report
|
| 2006-212 |
HYDRO ONE NETWORKS INC. |
Build 50/83 MVA, 230-27.6 kV Transformer Station |
New Supply Point |
83 MVA
|
In-Service
|
Active |
Final Draft Report
|
| 2006-214 |
ONTARIO POWER GENERATION INC. |
Pickering GS |
New Generation |
76 MW
|
In-Service
|
Complete |
Report
|
| 2006-215 |
HYDRO ONE NETWORKS INC. |
Cambridge Preston TS |
Transmission |
250 MVA
|
Q4-2007
|
Active |
Final Draft Report
|
| 2006-216 |
REGIONAL POWER INC. |
Town of Mobert |
New Generation |
11.11 MVA 9.44 MVA
|
Q2-2010 Q2-2010
|
Complete |
Final Report Final Report
|
| 2006-220 |
HYDRO ONE NETWORKS INC. |
Claireville TS |
Transmission |
- |
Q4-2009
|
Complete |
Report
|
| 2006-221 |
HYDRO ONE NETWORKS INC. |
Meadowvale TS/Halton TS |
Low Voltage Reactive Compensation |
21.6 MVAR 32.4 MVAR
|
Q2-2007 In-Service
|
Complete |
Report
|
| 2006-223 |
HYDRO ONE NETWORKS INC. |
Porcupine TS, Kirkland Lake TS |
Reactive Compensation |
- |
Q4-2010
|
Active |
Final Draft Report Diagrams
|
| 2006-224 |
HYDRO ONE NETWORKS INC. |
Milton-Claire 500kV ROW Intersects R21T/R19T Pleas |
Transmission |
- |
Q2-2010
|
Complete |
Report
|
| 2006-225 |
HYDRO ONE NETWORKS INC. |
Woodstock, Ontario |
New Supply Point |
41 MVA
|
In-Service
|
Active |
Final Draft Report
|
| 2006-226 |
NORTH AMERICAN PALLADIUM |
Lac Dec Iles Mine (90km north of Thunder Bay) |
Additional Load |
10
|
Under Construction
|
Complete |
Final Report
|
| 2006-227 |
HYDRO ONE NETWORKS INC. |
Township of Tosoronto-Cnty Road 5 & County Road 15 |
New Supply Point |
- |
In-Service
|
Active |
Final Draft Report
|
| 2006-228 |
HYDRO ONE NETWORKS INC. |
Town of Red Lake |
Additional Load |
- |
In-Service
|
Complete |
Final Draft Report
|
| 2006-230 |
HYDRO ONE NETWORKS INC. |
Vicinity-Winston Churchill Blvd, North-West Miss |
New Supply Point |
- |
Q2-2010
|
Active |
Final Draft Report
|
| 2006-231 |
HYDRO ONE NETWORKS INC. |
North-West Brampton, Ontario |
New Supply Point |
- |
Q2-2008
|
Active |
Final Draft Report
|
| 2006-233 |
HYDRO ONE NETWORKS INC. |
Detweiler TS, Orangeville TS |
Reactive Compensation |
245 MVAR
|
Under Construction
|
Active |
Final Draft Report
|
| 2006-236 |
BROOKFIELD WIND POWER CORPORATION |
Near the town of Comber, Southwestern Ontario |
New Generation |
150 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2006-237 |
BROOKFIELD WIND POWER CORPORATION |
North of SSM, Twnp of Spider, Northern Ontario |
New Generation |
150 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2006-238 |
HYDRO ONE NETWORKS INC. |
Mid-town Toronto |
Transmission |
- |
Q2-2010
|
Active |
Final Draft Report(2)
|
| 2006-239 |
ONTARIO POWER GENERATION INC. |
70km Northeast of Kapuskasing |
New Generation |
441 MW
|
|
Active |
|
| 2006-240 |
TORONTO HYDRO ENERGY SERVICES INC. |
Toronto, Ontario, Canada |
New Generation |
30 MVA
|
-
|
Withdrawn |
|
| 2006-241 |
ONTARIO POWER GENERATION INC. |
Twnp of Gillies Timber Limit, Dist of Temiskaming |
New Generation |
44 MW
|
|
Complete |
Final Report
|
| 2006-245 |
HYDRO OTTAWA LIMITED |
Cyrville Road Ottawa |
New Supply Point |
- |
Q3-2008
|
Complete |
Final Report
|
| 2006-246 |
HYDRO ONE NETWORKS INC. |
Richview TS |
Transmission |
- |
Q4-2009
|
Active |
|
| 2006-247 |
HYDRO ONE NETWORKS INC. |
Lakehead TS |
Reactive Compensation |
60 MVAR
|
Q4-2009
|
Active |
Final Draft Report
|
| 2006-248 |
HYDRO ONE NETWORKS INC. |
On the existing R21T/R19T, Plesant tap R-O-W |
Transmission |
- |
Q2-2010
|
Active |
Final Draft Report
|
| 2006-250 |
HYDRO ONE NETWORKS INC. |
Southwestern Ontario |
Transmission |
- |
Q4-2011
|
Active |
Final Draft Report Diagrams
|
| 2006-251 |
TORONTO HYDRO-ELECTRIC SYSTEM LIMITED |
Metro Tor Conv Ctre & John Street Pumping Station |
New Generation |
11 MW
|
Under Construction
|
Complete |
Report
|
| 2006-252 |
ONTARIO POWER GENERATION INC. |
Beck 1 Generation Station |
New Generation |
68.5 MVA
|
Q4-2008
|
Complete |
Final Report
|
| 2006-253 |
HYDRO ONE NETWORKS INC. |
Woodstock, Ontario |
Transmission |
- |
Q2-2010
|
Active |
Final Draft Report
|
| 2007-254 |
ONTARIO POWER GENERATION INC. |
Mississauga |
New Generation |
900 MW
|
Q1-2011
|
Active |
|
| 2007-257 |
HYDRO ONE NETWORKS INC. |
St. Catherines Area |
Transmission |
- |
Q2-2009
|
Active |
Final Draft Report
|
| 2007-258 |
HYDRO ONE NETWORKS INC. |
City of St. Catherine |
Transmission |
- |
Q2-2010
|
Active |
Final Draft Report
|
| 2007-259 |
LAKESHORE GOLD CORP |
Timmins (Hwy 101 W & 144) |
Additional Load |
- |
Q3-2007
|
Complete |
Report
|
| 2007-260 |
HYDRO ONE NETWORKS INC. |
Aldborough Twp, County of Chatham-Kent |
New Supply Point |
57 MVA
|
Q4-2010
|
Active |
Final Draft Report
|
| 2007-263 |
HYDRO ONE NETWORKS INC. |
Municipality of Windsor and Essex County |
Transmission |
500 MVA
|
-
|
Withdrawn |
Final Draft Report
|
| 2007-264 |
HYDRO ONE NETWORKS INC. |
9513 Goreway Dr, Brampton (at existing Goreway TS) |
New Supply Point |
175 MVA
|
Q2-2010
|
Active |
Final Draft Report
|
| 2007-265 |
HYDRO ONE NETWORKS INC. |
Keith TS |
Transmission Upgrades |
500 MVA
|
Q1-2010
|
Active |
|
| 2007-266 |
ONTARIO POWER GENERATION INC. |
Geographic Township of Gouin, District of Sudbury |
New Generation |
5.6 MVA
|
Q4-2010
|
Complete |
Final Report
|
| 2007-267 |
Dover Wind Power Partnership |
North Kent - Chatham Kent Area |
New Generation |
40 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2007-268 |
Raleigh Wind Power Partnership |
North Kent - Chatham Kent Area |
New Generation |
199.5 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2007-269 |
HYDRO ONE NETWORKS INC. |
Multiple Stations |
New Generation |
- |
|
Active |
Final Draft Report
|
| 2007-270 |
WIKWEMIKONG UNCEDED INDIAN RESERVE |
Wikwemikong, Ontario |
New Generation |
124 MW
|
|
Active |
|
| 2007-272 |
CPV CANADA DEVELOPMENTS INC. |
2384 Dundas Road South, Cambridge, Ontario |
New Generation |
500 MVA
|
Q2-2010
|
Active |
|
| 2007-273 |
BROOKFIELD WIND POWER CORPORATION |
Renfrew Area-Vicinity of Mount Chute GS, East ON |
New Generation |
99 MW
|
Q4-2009
|
Active |
|
| 2007-274 |
BROOKFIELD WIND POWER CORPORATION |
Near Madawas-Vicinity of Wallance TS, Eastern ON |
New Generation |
199.5 MW
|
Q4-2009
|
Active |
|
| 2007-275 |
FPLE CANADIAN WIND, ULC |
Huron County, Ontario |
New Generation |
63 MW
|
|
Part 1 SIA Comp |
|
| 2007-276 |
FPLE CANADIAN WIND, ULC |
Lambton County, Ontario |
New Generation |
249 MW
|
Q4-2013
|
Part 1 SIA Comp |
|
| 2007-277 |
FPLE CANADIAN WIND, ULC |
Huron County, Ontario |
New Generation |
87 MW
|
|
Part 1 SIA Comp |
|
| 2007-278 |
FPLE CANADIAN WIND, ULC |
Lambton County, Ontario |
New Generation |
84 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2007-279 |
BROOKFIELD POWER |
Aguasabon River |
New Generation |
10 MW
|
|
Active |
|
| 2007-280 |
FPLE CANADIAN WIND, ULC |
Lambton and Middlesex Counties, Ontario |
New Generation |
349.5 MW
|
Q4-2013
|
Part 1 SIA Comp |
|
| 2007-281 |
BUTTCON LTD. |
Windsor, Ontario |
New Generation |
14 MW
|
|
Complete |
Final Report
|
| 2007-282 |
KABINAKAGAMI POWER LP |
Kabinakagami River north Hwy 11, south Roger's Rd |
New Generation |
60 MW
|
Q4-2015
|
Active |
|
| 2007-283 |
CPV CANADA DEVELOPMENTS INC. |
768 Haldimand Rd 55, Jarvis,ON, Lot7, Concession 7 |
New Generation |
1758 MVA
|
Q4-2012
|
Active |
|
| 2007-284 |
TERRACE BAY PULP INC. |
Terrace Bay, Ontario |
New Generation |
29.5 MVA
|
Q2-2008
|
Complete |
Final Report
|
| 2007-285 |
4444388 CANADA INC. |
Beardmore, Ontario |
New Generation |
10 MW
|
Q3-2009
|
Active |
|
| 2007-286 |
SKYPOWER CORP. |
Parry Island, Ontario |
New Generation |
150 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2007-287 |
AIM POWERGEN CORPORATION |
County of Chatham-Kent north of Chatham |
New Generation |
150 MW
|
Q4-2010
|
Part 1 SIA Comp |
|
| 2007-288 |
AIM POWERGEN CORPORATION |
County of Chatham-Kent Near the Town of Blenheim |
New Generation |
99 MW
|
Q4-2010
|
Part 1 SIA Comp |
|
| 2007-289 |
AIM POWERGEN CORPORATION |
Essex County Near the Town of Tilbury |
New Generation |
40 MW
|
Q4-2010
|
Part 1 SIA Comp |
|
| 2007-290 |
AIRTRICITY CANADA LTD. |
Chatham-Kent, Municipality |
New Generation |
100 MW
|
|
Active |
|
| 2007-291 |
SKYPOWER CORP. |
North of Picton, ON |
New Generation |
99 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2007-292 |
SKYPOWER CORP. |
Near Foymount, South of Lake Clear |
New Generation |
150 MW
|
Q4-2009
|
Part 1 SIA Comp |
|
| 2007-293 |
AIR ENERGY TCI INC. (TCI RENEWABLES) |
Vicinity of Adelaide, Adelaide-Metcalfe, Ontario |
New Generation |
74 MW
|
Q4-2011
|
Part 1 SIA Comp |
|
| 2007-294 |
ONTARIO POWER GENERATION INC. |
Township of Pinard, District of Cochrane |
New Generation |
28 MVA
|
Q4-2012
|
Active |
|
| 2007-295 |
HYDRO ONE NETWORKS INC. |
Buchanan TS, Middleport TS, Nanticoke TS |
Reactive Compensation |
1700 MVAR
|
Q2-2009
|
Active |
Final Draft Report
|
| 2008-296 |
HORIZON HYDRO INC. |
Township of Gery, On, Canada |
New Generation |
5 MW
|
Q4-2011
|
Active |
|
| 2008-297 |
SUNCOR ENERGY INC. |
Chatham-Kent Area, South-Western Ontario |
New Generation |
76 MW
|
|
Part 1 SIA Comp |
|
| 2008-298 |
HYDRO ONE NETWORKS INC. |
Vicinity of the Toyota Woodstock Plant |
New Supply Point & Transmission |
117 MVA
|
Q2-2010
|
Active |
Final Draft Report
|
| 2008-301 |
ENBRIDGE INC. |
Municipality of Kincardine, Ontario |
New Generation |
99 MW
|
Q4-2011
|
On-Hold |
|
| 2008-302 |
ENBRIDGE INC. |
Town of Saugeen Shores, Ontario |
New Generation |
49.5 MW
|
Q4-2011
|
On-Hold |
|
| 2008-307 |
ONTARIO CLEAN POWER FRIDAY LAKE INC. |
Temagami, Ontario |
New Generation |
100 MW
|
Q4-2009
|
Active |
|
| 2008-309 |
RICHVIEW RESOURCES INC. |
Pickle Lake, Ontario |
New Supply Point |
9 MW
|
Q4-2010
|
Active |
|
| 2008-310 |
SUN COKE INTERNATIONAL |
Nanticoke, ON |
New Generation |
154 MVA
|
Q1-2011
|
Part 1 SIA Comp |
|
| 2008-312 |
NORTHGATE MINERALS CORPORATION |
Matachewan, Ontario |
New Supply Point |
- |
|
Active |
|
| 2008-314 |
GENGROUTH MERLIN LP. |
Chatham-Kent, Near Town of Merlin |
New Generation |
99 MW
|
Q1-2010
|
Part 1 SIA Comp |
|
| 2008-315 |
BROOKFIELD RENEWABLE POWER INC. |
Algoma x Mississagi Area |
New Generation |
10 MW
|
|
Active |
|
| 2008-318 |
HYDRO ONE NETWORKS INC. |
Municipality of Windsor and Essex County |
Transmission |
166.6 MVA
|
Q4-2012
|
Active |
|
| 2008-319 |
CANADIAN SHIELD WIND POWER-DIV OF PTERAGEN CANADA |
Comm. of Garson-Municipality of Greater Sudbury |
New Generation |
100 MW
|
Q3-2012
|
Part 1 SIA Comp |
|
| 2008-320 |
POWERSTREAM INC. |
NW corner of Rodick Rd & Hwy 407, Markham, ON |
New Supply Point |
- |
Q4-2009
|
Active |
|
| 2008-321 |
TransCanada Corporation |
Chatham & Kent (S of Tilbury) |
New Generation |
172.5 MW
|
Q4-2012
|
Part 1 SIA Comp |
|
| 2008-322 |
TransCanada Corporation |
Orangeville |
New Generation |
48 MW
|
Q4-2012
|
Part 1 SIA Comp |
|
| 2008-323 |
TORONTO HYDRO ENERGY SERVICES INC. |
1 Carlingview Dr., Toronto, ON |
New Generation |
56.3 MVA 14.85 MVA
|
Q4-2012 Q4-2012
|
Part 1 SIA Comp |
|
| 2008-325 |
BOWARK ENERGY LTD. |
Chatham-Kent; Harwich; Howard & Raleigh townships |
New Generation |
150 MW
|
Q4-2011
|
Part 1 SIA Comp |
|
| 2008-326 |
AIR ENERGY TCI INC. (TCI RENEWABLES) |
East of Nanticoke, Ontario |
New Generation |
80 MW
|
Q4-2011
|
Part 1 SIA Comp |
|
| 2008-331 |
TWENTY TWO DEGREE ENERGY CORPORATION |
Holmesville, Central Huron, County of Huron |
New Generation |
200 MW
|
|
Part 1 SIA Comp |
|
| 2008-333 |
NORTHLAND POWER INC. |
Park Rd. South, Oshawa, ON |
New Generation |
71.176 MVA 71.176 MVA 38.8 MVA
|
Q2-2013
|
Part 1 SIA Comp |
|
| 2008-334 |
IPC ENERGY |
Twshp of Dawn-Euphemia, Lambton Cty Chatham-Kent |
New Generation |
- |
Q3-2012
|
Part 1 SIA Comp |
|
| 2008-335 |
RENEWABLE ENERGY SYSTEMS CANADA INC |
near Ridgetown, Ontario |
New Generation |
101.97 MW
|
Q3-2010
|
Part 1 SIA Comp |
|
| 2008-336 |
RENEWABLE ENERGY SYSTEMS CANADA INC |
near Madawaska, Ontario |
New Generation |
49 MW
|
Q3-2010
|
Part 1 SIA Comp |
|
| 2008-337 |
RENEWABLE ENERGY SYSTEMS CANADA INC |
west of Dorion, Ontario |
New Generation |
100 MW
|
Q3-2010
|
Part 1 SIA Comp |
|
| 2008-338 |
CANADIAN HYDRO DEVELOPERS INC |
North Middlesex |
New Generation |
34.5 MW
|
Q3-2012
|
Part 1 SIA Comp |
|
| 2008-341 |
WINDLECTRIC INC. |
Amherst Island |
New Generation |
200 MW
|
Q4-2013
|
Part 1 SIA Comp |
|
| 2008-342 |
KRUGER INC. |
Town of Marathon |
New Generation |
25.3 MVA
|
Q4-2010
|
Part 1 SIA Comp |
|
| 2008-343 |
KRUGER INC. |
Municipality of Chatham-Kent |
New Generation |
101.2 MVA
|
Q4-2011
|
Part 1 SIA Comp |
|
| 2008-344 |
BOWATER CANADIAN FOREST PRODUCTS INC. |
Thunder Bay |
New Generation |
62.64 MW
|
|
Part 1 SIA Comp |
|
| 2008-347 |
NORTHLAND POWER INC. |
Manitoulin Island |
New Generation |
85 MW
|
Q3-2010
|
Part 1 SIA Comp |
|
| 2008-349 |
AIM POWERGEN CORPORATION |
Tilsonburg |
New Generation |
50 MW
|
Q4-2008
|
Part 1 SIA Comp |
|