| |
|
|
|
|
Within Connection Assessments
Related Information
Connection Assessments
Introduction - Connection Assessment and Approval
In accordance with the Market Rules, Chapter 4, Section 6, anyone planning to
construct a new or modified connection to the IESO-controlled grid is required to apply to
the IESO for inclusion in the Connection Assessment and Approval (CAA) process.
The Connection Assessment and Approval process allows the IESO to assess the
impact of new or modified connections on the reliability of the integrated power
system. A connection applicant does not have to be a Market Participant in order
to apply for Connection Assessment and Approval; however, the required participant
authorization and facility registration processes must be completed prior to
participation in the IESO-administered markets.
Obtaining an Assessment or Approval provides an
overview of the connection process, from submitting an application through to gaining
approval. It includes the relevant forms and procedures.
The Hydro One Connection Impact Assessment application and the IESO System Impact Assessment application form for generation facilities have been combined to improve the connection assessment process.
The Connection Assessment and Approval process requires the IESO to assess all
proposals for connection to the IESO-controlled grid. In accordance with the CAA
procedures, those projects that are not expected to have a significant impact on
the IESO-controlled grid are only required to undergo an Expedited System Impact Assessment.
Status of System Impact Assessment Applications received before April 30, 2005
This list provides the status of all transmission, load, generation and ancillary services connection proposals that have submitted an SIA application before April 30, 2005 and subsequently executed an SIA agreement. Queuing principles are still applicable to these proposals. Links are provided for Preliminary Assessment reports (no longer applicable) and SIA reports.
Status of System Impact Assessment Applications received on or after April 30, 2005
This list contains all transmission, load, generation and ancillary services connection proposals that have submitted an SIA application on or after April 30, 2005 and subsequently executed an SIA agreement. Queuing principles are not applicable to these proposals. Links are provided for SIA reports.
Status of System Impact Assessment Applications in the Committed Generation Project Queue
This list contains all generation projects that are deemed to be committed based on the requirements in sections 3.3.1 and 3.3.2 of market manual 2.10. Queuing principles are still applicable to these proposals. Links are provided for SIA reports.
Status of Expedited System Impact Assessment Applications
This list contains all transmission, load, generation and ancillary services connection proposals that meet the requirements described in section 9.2. Links are provided for expedited SIA reports.
|
| |